T4 — Human-essentialPhase 7 of 13
Plumbing Rough-In
Mechanical Rough-In
Description
Install drain-waste-vent (DWV) piping, water supply lines, and stub-outs for all fixtures per plumbing plan. DWV first — it is rigid and gravity-dependent. Supply lines flex around DWV. Pressure test before closing walls.
Tools (ML1 Confirmed)
- pipe cutter
- soldering torch
- pipe wrench
- level
- drill
Atomic Primitives
cutjoinroutetest
2-3
Crew Size
16-24h
Estimated Hours
7
Phase
T4
Robot Tier
Other Tasks in Phase 7: Mechanical Rough-In
Related Resources
plumbing rough inDWV piping installationresidential plumbing roughwater supply rough in