T1 — Near-term automationPhase 4 of 13
Structural Wall Sheathing
Framing — Walls
Description
Install 7/16-inch or 1/2-inch OSB structural sheathing on exterior walls for lateral bracing. Nailing schedule per shear wall design — typically 3-inch nails at 4 inches on center at edges for high-shear panels. Stagger vertical joints.
Tools (ML1 Confirmed)
- framing nailer
- circular saw
- chalk line
- tape measure
- hand tools
Atomic Primitives
positionfastencutverify
3-4
Crew Size
6-10h
Estimated Hours
4
Phase
T1
Robot Tier
Other Tasks in Phase 4: Framing — Walls
Related Resources
structural sheathing wallsOSB wall sheathingshear wall nailingwall bracing sheathing